PIPE LINE CONSTRUCTION and SERVICE
CALIBRAGE [KALİBRAJ] AND CLEANUP OPERATION
CALIBRAGE [KALİBRAJ] AND CLEANUP OPERATION
DISCHARGE
PRELIMINARY DRYING
Akıllı Pig
DRYING
PIPE LINE EXAMINATION
Referanslar
PRELIMINARY DRYING
Yeni Sayfa 11

There may be some filling water which leaked to the backside of the discharge pigs inside every test part discharge process of which has
been completed. It is important to have these water amounts collected especially in calyx areas discharged outside within the system before
the actual drying process starts. Generally it is done via disposing a Bi-Di pig and sponge pigs at different intensities from the backside.
The number and type of sponge pigs will be evaluated considering the physical condition of the pigs coming up from the receiving headpiece.
 

Print

| construction | Yol Köprü İnşaatı | Zemin Edütü | industry installation | pipe line | pipe line construction and service | Boru Hattı Servisi | Enerji | power plants and transformers | Power Plant | Kurumsal | İletişim | our environment policy | our quality policy | our mission & our vission | about us |